On December 16, 2018, the steel poles FAT test for project 230kv transmission line in DR-Congo were carried out in our company's steel pole test workshop. Participating in the test were representatives of the Spanish EPC and representatives team from the Democratic State Grid of DR- Congo. A total of six representatives came to witness the results of the FAT test. There had 6 types of steel pole were carried out the FAT test. Items of FAT test includes: Material Test, Proofing Test and Loading Test. Customers are very satisfied with the test results of our products. The higher test results show that the product quality of our steel poles is very reliable.